Monitoring: 1

Total Panjang

397 m

Total Dikerjakan

17 m

Sisa

380 m

Aspal
5/34 m
Beton
6/55 m
Tanah
6/99 m
Syphon
99 m
Monitoring Per Patok
Patok DN Aspal Beton Tanah Syphon Total HDPE GI Jembatan Total Segmen Dikerjakan Sisa
P1-P2 100 1 / 1
Sisa: 0 m (100%)
2 / 11
Sisa: 9 m (18.18%)
2 / 55
Sisa: 53 m (3.64%)
55 122 55 177 5 172
P0-P1 50 4 / 33
Sisa: 29 m (12.12%)
4 / 44
Sisa: 40 m (9.09%)
4 / 44
Sisa: 40 m (9.09%)
44 165 55 220 12 208
Rekap Berdasarkan DN
DN AspalBetonTanahSyphon Total HDPEGI JembatanTotal Segmen DikerjakanSisa
50 33 44 44 44 165 55 220 12 208
100 1 11 55 55 122 55 177 5 172