Monitoring: fuja

Total Panjang

272 m

Total Dikerjakan

39 m

Sisa

233 m

Aspal
13/87 m
Beton
13/267 m
Tanah
13/237 m
Syphon
69 m
Monitoring Per Patok
Patok DN Aspal Beton Tanah Syphon Total HDPE GI Jembatan Total Segmen Dikerjakan Sisa
P0-P1 100 3 / 10
Sisa: 7 m (30%)
3 / 10
Sisa: 7 m (30%)
3 / 10
Sisa: 7 m (30%)
8 38 9 47 9 38
P1-P2 50 4 / 10
Sisa: 6 m (40%)
4 / 70
Sisa: 66 m (5.71%)
4 / 9
Sisa: 5 m (44.44%)
5 94 33 127 12 115
P1-P3 50 6 / 9
Sisa: 3 m (66.67%)
6 / 9
Sisa: 3 m (66.67%)
6 / 60
Sisa: 54 m (10%)
10 88 10 98 18 80
Rekap Berdasarkan DN
DN AspalBetonTanahSyphon Total HDPEGI JembatanTotal Segmen DikerjakanSisa
50 57 237 207 45 546 129 675 30 645
100 30 30 30 24 114 27 141 9 132