| Patok | DN | Aspal | Beton | Tanah | Syphon | Total HDPE | GI Jembatan | Total Segmen | Dikerjakan | Sisa |
|---|---|---|---|---|---|---|---|---|---|---|
| P0-P1 | 100 |
3 /
10 Sisa: 7 m (30%) |
3 /
10 Sisa: 7 m (30%) |
3 /
10 Sisa: 7 m (30%) |
8 | 38 | 9 | 47 | 9 | 38 |
| P1-P2 | 50 |
4 /
10 Sisa: 6 m (40%) |
4 /
70 Sisa: 66 m (5.71%) |
4 /
9 Sisa: 5 m (44.44%) |
5 | 94 | 33 | 127 | 12 | 115 |
| P1-P3 | 50 |
6 /
9 Sisa: 3 m (66.67%) |
6 /
9 Sisa: 3 m (66.67%) |
6 /
60 Sisa: 54 m (10%) |
10 | 88 | 10 | 98 | 18 | 80 |
| DN | Aspal | Beton | Tanah | Syphon | Total HDPE | GI Jembatan | Total Segmen | Dikerjakan | Sisa |
|---|---|---|---|---|---|---|---|---|---|
| 50 | 57 | 237 | 207 | 45 | 546 | 129 | 675 | 30 | 645 |
| 100 | 30 | 30 | 30 | 24 | 114 | 27 | 141 | 9 | 132 |